A submerged membrane bioreactor is only as good as its commissioning. The steps below cover the clean-water run, seeding, the start of filtration, the operating parameters to watch, and the maintenance routine — aeration-pipe cleaning, chemical cleaning and fault-finding — that decides how long the membranes last.
1. Running a Submerged MBR Module
1.1 Checks and Settings Before the Clean-Water Run
(a) Confirm again that the air and wastewater pipes are correctly connected.
(b) Confirm that the membrane cassette is properly fixed on the aeration box.
(c) Confirm that the reaction tank holding the module has been cleaned, and open the protective cover. Soil and dust can damage the membrane elements.
(d) Before filling the tank with clean water, open the air release valve to expel air from the membrane elements.
(e) Fill with clean water — tap water or filtered water — up to the operating level.
(f) Close the air release valve once filling is complete.
1.2 The Clean-Water Run Itself
(a) After the aeration blower starts, confirm the aeration rate and the evenness of the aeration. Foam may appear during the clean-water run. It usually comes from insoluble, biodegradable hydrophilic substances in the membrane and can be ignored; carry on running.
(b) Where one blower serves several modules, each module must receive the same air volume. If the volumes differ markedly, check the piping arrangement — branch pipe diameters and the like — and each air line until the supply is equalised.
(c) During the clean-water run, check the performance of the control equipment.
(d) During the clean-water run, measure the transmembrane pressure and the water temperature at the design filtration rate — normal, maximum and minimum — and record them.
(e) Stop filtration and aeration as soon as the performance test is finished.
2. Seeding with Sludge
Seeding is mandatory. Filtering raw water through the membrane without seeding can foul the membrane much earlier than expected.
(1) Have seed sludge from a plant treating the same kind of wastewater ready. Sludge at a mixed liquor concentration of about 20,000 mg/L is recommended.
(2) Start feeding raw water immediately after seeding. Feed it through a fine screen with openings of 5 mm or less so that debris is removed.
(3) Dose enough seed to bring the mixed liquor in the membrane tank above 7,000 mg/L. Do not use commercial seeding agents.
3. Starting Filtration
Once seeding is complete, start aeration first, then filtration, and begin raw-water feed at the same time. When the filtration rate has stabilised, measure and record the transmembrane pressure and water temperature at the actual filtration rate.
4. Operating Management
Standard operating conditions. Filtration performance is only maintained if mixed liquor concentration, viscosity, dissolved oxygen and pH all stay inside their proper ranges. Where the raw water carries much debris or coarse suspended solids, or a high proportion of oil and grease, appropriate pretreatment is essential. If an antifoam has to be added to control foam in the membrane tank, use an alcohol-type antifoam that does not readily foul the membrane.
The ranges below are standard conditions, not a prescription that fits every wastewater: actual values shift with the duty, and sludge characteristics in particular.

Standard operating conditions for a submerged MBR module.
| Parameter | Typical range | Note |
|---|---|---|
| MLSS | 7,000–18,000 mg/L | Below the range, performance may not be reached |
| Sludge viscosity | 250 mPa·s or less | High viscosity means fouling sludge |
| Dissolved oxygen | 1 mg/L or more throughout | Raise aeration if below, up to the maximum |
| pH | 6–8 | Adjust with acid or alkali |
| Water temperature | 15–40 °C | Cool or insulate where possible |
What to record. Module performance changes with raw-water quality and with the operating conditions set. To keep operation stable, record the following quantities so that trends and peculiarities in your own plant become visible:
(1) Aeration rate
(2) Air outlet pressure
(3) Permeate flow or membrane flux
(4) Transmembrane pressure (TMP)
(5) Permeate quality — BOD, COD, turbidity, total nitrogen, total phosphorus
(6) Reaction tank water temperature
(7) Raw-water quality — BOD, COD, turbidity, total nitrogen, total phosphorus
(8) Waste sludge volume
(9) Dissolved oxygen
(10) pH in the membrane tank
(11) MLSS
(12) Sludge viscosity
(13) Sludge settleability (SV60 or SVI120)
5. Daily Checks
Stable module operation depends above all on aeration and on stable biological treatment. Check the following every day.
Transmembrane pressure. Watch its stability. A sudden rise means the membrane is fouling, which may be caused by abnormal aeration or by deteriorating sludge. When that happens, check the parameters below and take the necessary action, chemical cleaning of the module among them.
Aeration. Check that the air rate is at the standard value and that the distribution is even. Where the rate is abnormal or the aeration clearly uneven, take the necessary steps: remove scale from the aeration pipes, check the installation, check the blower and adjust the aeration.
Colour and smell of the activated sludge. Healthy sludge is tea-brown, flocculent and free of unpleasant odour. If the appearance or smell is not as it should be, check MLSS, sludge viscosity, dissolved oxygen, pH, temperature and BOD load.
MLSS. The normal range is 7,000 to 18,000 mg/L. Outside it, the design performance may not be reached, so bring the concentration back: where MLSS is too low, seed more sludge or stop wasting; where it is too high, waste more sludge to the thickening tank.
Sludge viscosity. Normal sludge is below 250 mPa·s. Outside that, performance may suffer, so adjust the viscosity: where it is too high, replace sludge or increase wasting to the thickening tank.
Dissolved oxygen. Normal is 1 mg/L or more everywhere in the bioreactor. Below that, and provided the maximum aeration rate has not been reached, adjust the aeration.
pH. Normal is 6 to 8. Outside it, performance may fall short; adjust with acid or alkali.
Water temperature. Normal is 15 to 40 degrees Celsius. Outside it, performance may fall short, so cool or insulate the tank where possible.
Water level. Check that the bioreactor level is within its normal range. If it is not, check the level gauge, the permeate pump and the transmembrane pressure.
6. Maintenance
Items and frequency.
(1) Aeration pipe cleaning: once a day.
(2) Chemical cleaning of the membrane elements: when the transmembrane pressure at the same filtration rate is 5 kPa above the initial stable value, or every six months — whichever comes first.
(3) Replacement of the permeate hose: about every three years, though service conditions vary. Use the specified model, fit the hose firmly onto the outlet, and avoid putting strain on the membrane element and the permeate header connection. Details of the spare part are available from the membrane manufacturer.
7. Cleaning the Aeration Pipes
Scale blocking the aeration holes causes uneven aeration and membrane fouling, so the aeration pipes are cleaned once a day. Fitting an automatic valve to carry out the cleaning is recommended. Cleaning works by opening the air release valve so that the pressure in the pipe drops and sludge flows back into it; the air then flowing through the pipe carries the sludge out.

Sequence for cleaning an aeration pipe.
(i) Stop filtration.
(ii) Close valve V1.
(iii) Open cleaning valve V2. Sludge from the membrane tank then flows back through the aeration holes into the pipe and is discharged with the air.
(iv) Hold V2 open for one second.
(v) Close V2, then open V1.
(vi) Clean the other line in the same way.
(vii) Close valve V3.
(viii) Open cleaning valve V4, so that sludge again flows back through the aeration holes and out with the air.
(ix) Hold V4 open for one second.
(x) Close V4, then open V3.
(xi) Restart filtration.
8. Chemical Cleaning
Chemical cleaning is required when the transmembrane pressure has risen too far, which happens when the pores at the membrane surface become blocked. The interval is set as follows:
(1) Clean when the transmembrane pressure at the same filtration rate is 5 kPa above the initial stable value, or every six months, whichever comes first.
(2) Where the pressure is rising quickly, clean as soon as possible: early chemical cleaning is effective at clearing pore blockage at the membrane surface.
(3) If the 5 kPa rise occurs within six months, note how long it took. Putting chemical cleaning on a routine footing extends membrane life effectively.
Chemicals. Choose the cleaning chemical to suit the foulant. Sodium hypochlorite is used for organic fouling, oxalic acid and citric acid for mineral scale and metal deposits. All three are hazardous on contact with skin and eyes, so read the material safety data sheet before use, wear goggles and gloves, and follow the sheet's instructions if the chemical touches the skin. Keep them away from strong oxidants and strong alkali, do not let containers be tipped, dropped, struck or dragged, do not let dust or vapour escape, keep containers closed after use, wash hands and face and rinse the mouth afterwards, and use local exhaust ventilation where cleaning is done indoors. Store in a corrosion-resistant tank, out of direct sunlight, closed against the air and in a cool, well-ventilated place.
9. Carrying Out a Chemical Clean
Chemical solution is fed slowly through the permeate header until the element is full, so that it seeps through the membrane from the inside out. Feed it under gravity, never under pressure.
Where the chemical tank sits below the module.
(a) Confirm that the chemical valve is closed and the chemical pump stopped.
(b) Bring the chemical tank to the specified concentration.
(c) Stop filtration and close the permeate valve, keeping aeration running.
(d) Start the chemical pump and confirm that the solution is circulating.
(e) Open the chemical valve slowly to begin injection.
(f) Inject the specified volume, then stop the pump.
(g) Leave it to stand for the specified time, one to three hours.
(h) Close the chemical valve, open the permeate valve and restart filtration.
Where the chemical tank sits above the module.
(a) Confirm that the chemical valve is closed.
(b) Bring the tank to the specified concentration.
(c) Stop filtration and close the permeate valve, keeping aeration running.
(d) Open the chemical valve slowly and inject the specified volume under gravity.
(e) Leave it to stand for the specified time, one to three hours.
(f) Close the chemical valve, open the permeate valve and restart filtration.

Chemical cleaning sequence with the tank below the module.

Chemical cleaning sequence with the tank above the module.
Precautions. The permeate produced in the first period after cleaning still carries chemical and must be returned to the raw-water tank; where that is impossible, dispose of it as waste in accordance with local rules. Inject under gravity with the pressure below 10 kPa — pumping directly can exceed 10 kPa and damage the membrane elements, so never do it. Inject with the module submerged and at least 500 mm of water above it, for the operator's safety. Keep aeration running during cleaning, but lower the air rate if the chemical causes foaming in the tank. Cleaning works better warm, but do not exceed 40 degrees Celsius, and at low temperature cleaning may fail to restore membrane performance, so keep the tank as warm as is practical. When filtration restarts after cleaning, return the permeate to the raw water or treat it as waste until the chemical no longer affects quality.
10. Removing a Module
(1) Drain all the activated sludge from the bioreactor.
(2) To take out only the membrane element section, disconnect the permeate header; if the aeration section must come out as well, disconnect the air header too.
(3) To take out only the membrane element section, undo the bolts joining it to the aeration section, and the section can then be lifted out. Where the permeate header serves two cassettes, undo the bolts and remove the header.
(4) If the aeration section has to come out, release the anchor fixings, and it can then be lifted out.
11. Fault-Finding
The usual module faults are abnormal aeration, a rising transmembrane pressure with falling permeate flow, and deteriorating permeate quality. Work through the likely causes in turn: check the aeration pipe and blower first, since blocked aeration holes are the commonest single cause of both fouling and poor permeate; then check the sludge — viscosity, MLSS and settleability — and finally the membrane itself, cleaning it chemically before assuming it has reached the end of its life. When leak-testing pipe joints and welds under pressure, do not change the pressure applied to the membrane element.